    摘要:

    通过对邯郸某深基坑桩锚式支护结构冠梁水平位移的现场监测,结合理论计算,研究分析了深基坑开挖过程中冠梁的变形特征,及冠梁位移影响因素。结果表明,冠梁位移随开挖深度的增加而增大,但位移并不是沿冠梁均匀增大,表现为中间位移大两侧位移小,个别测试点位移出现负值,以及施加预应力锚杆对冠梁位移的积极作用,从而认为在开挖过程中应考虑时空效应的影响。

    Abstract:

    Bassed On filed measured date and calculated result about the top beam horizontal deformation of the anchor piles retaining structure in Handan.systematical analyses of their effective aspects of the defor· mation of top beam,the deformation and the level deformation distribution of top beam alonng with the excavation of the deep pit are studied in this paper.The deformation of the top beam will be increscent alonging with the excavation of the deep.However,the deformation of the top beam is differ on the diffirent test point.It is concluded that in design the time—space effect should be considered.

    参考文献
    相似文献
    引证文献
引用本文

吴雄志,白金杰,贾志刚,梁凯,张晓延.桩锚支护体系冠梁水平位移试验研究[J].河北工程大学自然版,2008,25(4):4-6