Approach of setting project buffer based on the theory of unascertained rational number
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    利用乐观时间制定项目进度计划,对任务链各任务持续时间的区间数进行未确知量化,利用未确知有理数的加法运算求得进度计划的未确知完成期及其对应的完工可信度和累积可信度,采用累积可信度在90%的情况下所得的工期和乐观时间估计的工期计算缓冲区时间,并以此制定关键链项目进度计划。案例分析表明,采用未确知有理数理论和乐观时间制定的关键链计划能够缓解工程项目不确定性因素的影响,与传统带有安全时间的进度计划相比节省工期,具有可行性。

    Abstract:

    The project schedule was made according to the ptimistic time,the intervals of mission du-ration in the mission list were quantified unascertainedly, the unascertained completion time and itsreliability and cumulative reliability were obtained by use of the addition operation of unascertained rational numbers. The buffer time was calculated by the optimistic construction period and total project period when completion reliability was 90%,then the project schedule of the critical chain was established. The case study shows that the project schedule of the critical chain made by the theory of un-ascertained rational number and ptimistic time can relieve the effect of uncertainties and save the construction period compared with the traditional schedule.

    参考文献
    相似文献
    引证文献
引用本文

李万庆,赵哲.基于未确知有理数的工程项目缓冲区的确定[J].河北工程大学自然版,2012,29(1):81-84

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2011-10-25
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2015-01-12
  • 出版日期:
文章二维码