钻孔灌注桩施工过程对邻近隧洞影响数值分析
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:

国家自然科学基金资助项目(51579081,51379065)


Numerical analysis on bored pile construction for adjacent existing tunnel
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    针对单排钻孔灌注桩施工过程对邻近隧洞的影响问题,运用FLAC3D建立三维简化模型,分析隧洞与桩间距S、桩长L对既有隧洞变形的影响规律。研究结果表明:隧洞竖向位移与S大致呈分段线性变化规律;为保证桩基施工过程中的隧洞结构稳定,S不宜小于6 m;桩长改变了桩底与隧洞在水平位置的关系,对既有隧洞的位移影响表现为有峰顶的双段线,桩底高程宜避免位于隧洞拱顶和拱底之间。

    Abstract:

    Based on a cross-tunnel bridge construction project,the effects of two factors -the distance between tunnel and pile (S) and the length of the pile (L) on the tunnel deformation are analyzed in the FLAC3D model. The results showthat the vertical displacement of the tunnel and S are approximately piecewise linear. In order to ensure the stability of the tunnel structure during the construction of the pile foundation,S should not be less than 6m;Relative position between pile and the tunnel is determined by the length of pile,the bottom of the pile should be avoided at the arch of the tunnel.

    参考文献
    相似文献
    引证文献
引用本文

马文琪,朱珍德.钻孔灌注桩施工过程对邻近隧洞影响数值分析[J].河北工程大学自然版,2017,34(4):32-36